The Lone Peak Residence — modern ski-in home at Empire Pass

Case study · Empire Pass · Deer Valley

The Lone Peak Residence

A 7,200 sq ft ski-in/ski-out built on a 32% grade Empire Pass parcel. Six bedrooms organized around an interior courtyard, structural-glass entry corridor, snow-melt deck and walkways, certified passive-house envelope.

The build

A mountain contemporary home in Empire Pass · Deer Valley.

The Lone Peak Residence was Alder & Stone's most technically demanding 2024 delivery. The Empire Pass parcel sits on a 32% south-facing grade with a meaningful avalanche-shadow upslope, which dictated almost every structural decision from foundation to roofline. The homeowners — a multi-generational family relocating from Northern California — had a clear program in hand from the first consultation: six bedrooms organized so the grandchildren and grandparents could share a roof without sharing a hallway.

Architect Owen Alder organized the home around a south-facing interior courtyard, with the four secondary bedrooms in a two-story bar on the east elevation and the primary suite and au-pair quarters in a west-elevation pavilion. The courtyard fills with the morning light off Bald Eagle, and the structural-glass entry corridor at the home's spine doubles as a daylight collector through the shoulder seasons.

Construction superintendent Marisol Vega ran daily site operations across the 16-month build phase. The technical challenges — caisson piers to 22 feet, structural retention on three faces, snow-melt deck engineering, and a passive-house-certified envelope at 7,800 ft elevation — were planned for in Design Development rather than discovered in construction. The home passed Deer Valley ARR on first submission and the certificate of occupancy walked clean.

Floor plan + massing

How the home is organized.

Three pavilions arranged around a south-facing courtyard, connected by a structural-glass entry corridor. East pavilion: four secondary bedrooms over a basement-level games room with bunk room. West pavilion: primary suite over a private den, separated from the secondary wing by the courtyard. Center spine: open kitchen, living, and dining, with a 22-foot vaulted ceiling and a four-season conservatory at the south end. Au-pair quarters: one-bedroom suite over the heated three-car garage, with a separate exterior entrance off the motor court.

The Lone Peak Residence — south elevation at twilight, snow-melt deck
The Lone Peak Residence — courtyard with structural-glass corridor
The Lone Peak Residence — open kitchen with Carrara marble island

Finish-out specifications

What's in the actual spec book.

Schüco AWS 90 triple-glazed wood-clad windows
Reynaers CP 130 lift-and-slide doors at courtyard
Western Red Cedar exterior cladding, charred-shou-sugi finish
Dimensional Telluride Gold stone base, 18" course
Standing-seam Galvalume roof with snow-melt valley
Wide-plank reclaimed Douglas fir floors, 8" face
Sub-Zero + Wolf + Cove appliance package
Carrara marble island, 12-foot single slab
Custom walnut cabinetry, hand-built site shop
Lutron RadioRA whole-home lighting + Shades
Crestron AV / Lutron Athena climate integration
Passive-house-certified envelope, blower-door 0.4 ACH50
Geothermal ground-source heating, 12-loop field
Snowmelt walkways and drive — heated to 36 in. depth
Steel-and-glass entry corridor, custom Vermont fabrication
Belden Brick interior accents at courtyard hearth

Build timeline

How the 24 months sign to keys broke down.

Discovery + program
Weeks 1–4
Walk of two finalist Empire Pass parcels; multi-generational program brief; budget envelope.
Schematic design
Months 1–3
Three pavilion + courtyard scheme adopted; first ARR conceptual walk-through.
Design development
Months 3–6
Structural retention strategy; passive-house consultant onboarded; full FF&E specification.
ARR + permitting
Months 6–9
First-pass ARR approval; Deer Valley building department review; one engineering revision on snow-load.
Foundation + retention
Months 9–12
Caisson piers to 22 ft; concrete retention walls on three faces; site-built drainage.
Framing + envelope
Months 12–16
Engineered I-joist framing; Schüco window install; cedar cladding (charred onsite).
Mechanical + finishes
Months 16–22
Geothermal commissioning; Lutron + Crestron site programming; millwork install.
Final finishes + hand-off
Months 22–24
Punch list; mechanical training; pre-occupancy ARR final; certificate of occupancy walk.

We interviewed four firms. Owen was the only one who walked the slope before quoting — and the only one who said, plainly, that the corner of the lot we wanted the kitchen on wouldn't carry the structural load we needed. Two years later the kitchen is where it should have been from the first sketch, and the home has been the easiest thing in our lives.

K. & M. Holloway, Empire Pass · January 2024

Back to all featured builds →

Tell us about your project

Building something like this?

Send the program and the lot — we'll be candid about whether the timeline above is realistic for your project, and what would shift the price up or down.

Architect-led designNAHB Master BuilderBUILDER 100Est. 2001
Website by WorkspaceCMS.ai