Case study · Old Town · Park City

The Aspen House

A 5,400 sq ft tear-down + rebuild on a 1.2-acre Old Town parcel. The original 1920s heritage facade was stabilized, raised, and re-set on a fully-modern interior reorganized around a central kitchen and a long covered porch.

The build

A mountain contemporary on heritage facade home in Old Town · Park City.

The Aspen House is one of Alder & Stone's most architecturally delicate deliveries. The Old Town parcel had been in one family since 1958, with a 1923 miner's cottage and a 1971 lean-to addition that the new owners — a couple relocating from the Bay Area — bought specifically because they wanted to keep the heritage facade and the mature aspen grove along the rear lot line. Park City's historic-character district review board agreed in principle, but only on condition that the facade was retained intact through demolition and rebuild.

Construction superintendent Marisol Vega ran a six-month structural-stabilization phase before any demolition began. We sleeve-braced the heritage facade, lifted it 14 inches off the original foundation onto a steel-girder cradle, demolished the failing 1971 addition, replaced the original foundation with a full poured walkout, and re-set the heritage facade onto its new bearing. The neighbors photographed the lift-and-set day. The board's preservation officer attended.

The rebuilt interior is fully modern: an open kitchen-living-dining spine running the depth of the home, a primary suite tucked into the south wing, four secondary bedrooms over a finished walkout basement, and a 60-foot covered porch on the rear that reads as the home's social heart in summer. The accessory dwelling unit over the new three-car garage was permitted under Park City's then-new ADU code and serves as a long-term rental that defrays the property's carrying cost.

Floor plan + massing

How the home is organized.

Single-story heritage facade at the street; rebuilt two-story interior set back behind. Heritage entry corridor opens to a long kitchen-living-dining spine running north-south, with the kitchen at center and the great-room hearth at the south end. Primary suite at the south end of the upper story over the great room; four secondary bedrooms in a north-wing children's hall over the entry corridor. Finished walkout basement under the great room: family room, gym, two flex rooms. ADU: 800 sq ft one-bedroom flat over the detached three-car garage, with its own entry off the alley.

The Aspen House — stone-and-timber entry, heritage-inspired detailing
The Aspen House — open kitchen with Pietra Cardosa island
The Aspen House — long covered rear porch facing mature trees at the rear lot line

Finish-out specifications

What's in the actual spec book.

Heritage facade — restored 1923 cedar shingle and divided-lite windows
New construction — Sierra Pacific wood-clad windows, custom black-on-cedar
Western Red Cedar interior cladding at exposed ceiling beams
Telluride Gold dimensional stone, restored 1923 chimney + new hearth
Standing-seam Galvalume roof, 24-gauge on new construction
Wide-plank reclaimed white oak floors, 7" face
Sub-Zero / Wolf appliance package, full kitchen
Pietra Cardosa island, 11-foot single slab
Custom flat-panel walnut cabinetry, hand-built site shop
Lutron Caseta whole-home lighting + Shades
Spray-foam wall + roof, R-49 ceiling, R-23 walls
Two-stage gas-furnace HVAC with whole-home humidification
60-ft covered rear porch — open-rafter cedar, ipe deck
Heritage facade re-set — engineered steel girder bearing on new foundation
ADU — Wolf compact range, Bosch dishwasher, full kitchen + laundry
Heated drive + walkways at front; mature aspen grove preserved at rear

Build timeline

How the 20 months sign to keys broke down.

Discovery + heritage analysis
Weeks 1–6
Park City Historic Preservation Commission pre-application; facade structural survey.
Schematic design
Months 1–3
Heritage-facade-retained scheme adopted; HPC conceptual review.
Design development
Months 3–6
Steel-cradle lift-and-set engineering; ADU code review; FFE schedule.
HPC + permitting
Months 6–8
First-pass HPC approval; building permit; one revision on heritage-window restoration.
Facade stabilization
Months 8–10
Sleeve-bracing; site-built steel girder cradle; preservation officer site visits.
Demolition + lift-and-set
Months 10–12
1971 addition demolished; foundation excavated; facade lifted and re-set.
New construction framing
Months 12–16
Full poured walkout foundation; engineered I-joist framing; cedar siding.
Finishes + ADU
Months 16–20
Cabinetry install; ADU build-out; heritage-window restoration; mechanical training.

We bought the house for the aspen grove and the 1923 facade. Owen was the only architect who didn't try to talk us out of either one — he sketched the lift-and-set on the back of a napkin at the first meeting, and twenty months later we're sitting on the porch in May with the original front door behind us. That facade has stood here longer than any of us; now it stands on top of a home we'll grow old in.

R. & L. Chen, Old Town · March 2024

Back to all featured builds →

Tell us about your project

Building something like this?

Send the program and the lot — we'll be candid about whether the timeline above is realistic for your project, and what would shift the price up or down.